Published
At the Roberts Hill tunnel north and south portals, between North Boambee Road and Coramba Road, we will be doing shotcreting outside of approved construction hours for portal stabilisation work. Most concrete activities will be carried out during approved construction hours which are Monday to Friday from 7am to 6pm, and Saturdays from 8am to 1pm.

Due to higher temperatures during spring, summer and autumn, some work will be undertaken outside of approved construction hours from Monday 30 September 2024 until early 2025. This work will be Monday to Friday from 5:30am to 7am and 6pm to 7pm and Saturday from 7am to 8am and 1pm to 5pm.